Easton Airport Project Update – December 2024

Tenants and Users of Easton Airport,

We are pleased to share important updates about the progress of Easton Airport’s Airfield Modernization Program. This multi-phase initiative represents a significant investment in the future of aviation at Easton Airport, ensuring compliance with FAA safety standards, enhancing operational efficiency, and supporting the growth of our community.

2024: Completion of Phase One
The construction phase of the 2024 Airfield Modernization Program is now complete. This marks a major milestone in our commitment to modernization and safety improvements.

Looking Ahead: Phase Two and Three

  • 2025: The former Talbot County Business Center will be demolished to make way for the construction of the new 6,400-foot Runway 4/22 and safety areas.
    • No planned runway closures are expected in 2025.

  • 2026: Runway construction will begin and is expected to be completed by the end of the year. Project timelines and schedules will be communicated in advance.
    • Operational impacts and runway closures are anticipated in 2026.

Stay Connected

We encourage you to stay informed as the program progresses. Updates and public presentations are shared during Easton Airport Advisory Board meetings. Meeting summaries, operational impact logs, and additional resources are available online at www.eastonairport.com/projects.

As always, check NOTAMs

Finally, as we strive to modernize the airfield and strengthen its role as an aviation hub and economic engine for Talbot County, Maryland, we ask for a moment of your time to complete our survey: www.eastonairport.com/survey. Your feedback will guide our efforts to enhance services and ensure your continued satisfaction.

Thank you again for being a valued member of the Easton Airport community!

Sincerely,
Micah Risher
Easton Airport Manager