Our long awaited AWOS replacement project will begin on Monday, April 3rd and is scheduled to be complete by June 1, 2023. The operational impacts will be minimal, except for a “cut over” period in late May. Please check NOTAMS for real time updates regarding outages.
Construction equipment will enter the airfield via Gate 4 between Easton Jet and Trooper 6 Hangar. They will stage equipment in the grass area off the South Ramp. A new AWOS will be installed to the north of the current AWOS location. Once the new AWOS is installed and connected to the Control Tower, the old AWOS will be decommissioned. At not time should construction interfere with the operation. No impacts to any movement areas are anticipated.
If you have any questions or concerns, please reach out to the Airport Office 410-770-8055.